61 mile, 16-inch O.D. Sequestration Line

The Kemper pipeline is a 61 mile, 16-inch O.D. CO2 sequestration line designed to transport 8,200 tonnes per day (~3,000,000 tonnes per annum).

PCS Scope of Work

The PCS scope of work included client BD support, route development, geotechnical, engineering & design, survey, permitting, construction management, project controls, regulatory interface, as-built drawings, and commissioning/operations support. This project included 8 HDDs and 3 meter stations.